Housing development projects is the largest single line in the 2027 Public Sector Investment Programme (PSIP), at MVR 3.0 billion (USD 195 million). The total PSIP allocation is MVR 8.2 billion (USD 532 million) in the budget the People’s Majlis approved on 24 November.
Add the social housing line and housing loan equity, and housing-related items come to MVR 5.22 billion (USD 339 million), about 64 per cent of the programme. Road construction receives MVR 1.3 billion (USD 84 million). All dollar figures use MVR 15.42 to the dollar.

The housing lines
Housing development projects alone take 36.6 per cent of the PSIP. Social housing and community infrastructure is set at MVR 1.47 billion (USD 95 million), of which MVR 1.42 billion (USD 92 million) is for housing construction. Housing loan equity is MVR 750 million (USD 49 million).
The 64 per cent figure counts the whole social housing and community infrastructure line, and it assumes the three lines do not overlap.
Roads
Road construction is MVR 1.3 billion, or 15.9 per cent of the PSIP. That is less than half the housing development line.
Where the PSIP sits in the budget
The PSIP accounts for about 84 per cent of capital expenditure of MVR 9.8 billion (USD 636 million). It is 15.6 per cent of total expenditure of MVR 52.6 billion (USD 3.41 billion).
What the figures do not show
The four named lines, counting housing construction as part of social housing, add up to MVR 6.52 billion (USD 423 million), or 79.5 per cent of the PSIP.
For 2026, PSIP spending had reached MVR 5.1 billion (USD 331 million) by late October. The 2026 allocation is not given, so that number cannot be turned into a rate of delivery. The 2027 allocation is MVR 3.1 billion (USD 201 million) above it, though that sets a full-year plan against about ten months of spending.